National Summary

A total of 43 gangs were in the field during the week working on various grid projects, solar projects and biogas digesters projects in the 8 provinces of the country.During the week, 2 grid projects electrifying 11 institutions were energized (9 in Midlands and 2 in Mat North).In the week, 1 institutional solar Micro-grid powering 1 institution was also commissioned in, ward 8 Umguza District, Mat North Province.

Works in progress last week

4 projects were in progress to electrify 4 villages with a total of 118 homesteads last week

Work Done:

  • 2km HV hole digging complete
  • 5km HV pole planting complete
  • 6km of MV line bush clearing complete
  • 6km of hole digging completed

Grid projects energised

·        Mjena Business Centre and Clinic – Nkayi district in Ward 27. With 0.33km MV line. Energised on 29/05/2025 benefiting 12 Shops.

 

Solar projects energised

·   Hlabathi Primary School – Umguza District – commissioned and energised 28/05/2025, benefiting a total Ward 8 population of 900 including 220 students, and 7 Teachers

 

Work Done last week

5 projects were in progress to electrify 9 institutions in various districts of the province.

o       1.66km HV line and 0.39km MV line construction complete.

o       0.52km Bush clearing 100% complete, hole digging 60% complete

o       Battlefields Primary School and Secondary School – Internal wiring for 3 blocks was in progress.

 

Institutional Biogas Works in Progress

·        ZPCS Ntabazinduna – setting up the foundation as of 2 June2025 i.e at 20%

·        Khami Prison Medium Complex – 200 cubic meters biogas digester – pit excavations in progress 70% complete

Grid Projects Energised

One project powering two institutions was energised in the week under review

Chivare Clinic & Business Centre in Shamva district ward 18 – 3.2km of 11kV line, 0.72km MV line and 50kVA substation capacity energized on 30/05/25 benefiting 4 shops serving a population of around 4195 in the ward. The Clinic is not yet operational.

 

Work Done last week

3 projects are in progress to electrify 3 institutions in various Districts

–  1.2km of HV line survey completed

–  0.97km of MV line survey completed

– Material for 3 projects delivered to site

 

Institutional Biogas Works in progress

– Pit excavation for Mazowe VET College Biogas 50m3   and St Alberts High School Biogas 50m3 in Mt Darwin are now complete, mobilisation of construction materials is in progress.

–  Shamva Hospital and Jiti Secondary School in Shamva pit excavations are in progress.

 

Domestic Biogas Works in Progress

Identification of interested villagers is in progress.

·  To date, 40 homesteads (8 homesteads in Rushinga, 8 homesteads in Mt Darwin, 8 homesteads in Bindura, 8 homesteads in Shamva and 8 Homesteads in Mazowe) were identified and have started mobilising local materials and excavation of pits in preparation for the dome construction.

· Muyembe homestead in Bindura District – domestic biogas pit excavation complete. Project is 50% complete.

Grid Electricity Works

7 projects were in progress to electrify 20 institutions in various districts of the province. 6km of HV bush clearing complete.

 

 Community Solar Works

Nzvimbe Community solar in Makoni District.  Steel structures assembling and pillar casting still in progress – 23% done.

 

Domestic Biogas

Dumbarimwe Homestead in Mutare 9m3 digester, dome construction 95% in progr Ambasi Homestead in Makoni 9m3 digester, dome construction 90% in progress

 

Work Done last week

5 projects were in progress to electrify 7 institutions in various districts of the province

* 11.5km of HV line bush clearing, hole digging, pole positioning & erection done

* 5.1km of MV line surveying, bush clearing, hole digging and pole erection done.

 

Community Solar Mini Grid

* Dete Solar Mini Grid at 98% to completion

* Works in progress: Reconfiguration of the powerhouse, Plant civil works, Installation & programming of monitoring devices, Metering & billing system configurations.

 

Work Done last week

 8 projects were in progress to electrify 23 institutions in various districts of the province.

* 5km HV line survey completed

* 0.8km MV pole erection completed

Institutional Solar Micro Grids Works in Progress

Chimhodzi Primary and Secondary Schools: Installation of 1 x 10kW Solar System, construction of 1.41km MV line is now complete.  Internal wiring for Admin block, 1 Classroom Block and Staff houses is in progress, overall status at 80%.

Community Solar Mini-Grids

Chiwore: Scope –Erect 1 x 60kW Solar system, construct 5.7km LT lines connecting households and institutions.

Done: 5.7km MV line completed.  PV Solar Plant civil works were in progress – 80% complete.

*  Setting out and excavation of powerhouse foundation 100% complete

*  Concrete pouring for support pillars 90% complete

Institutional Biogas Works in progress

· St Paul’s Musami High – 50m3 biogas digester – Excavation works completed.  Foundation works in progress

· St Thomas Prison – 50m3 biogas digester – Excavation works in progress.

· St Ignatius High – 50m3 biogas digester – Excavation completed.  foundation works in progress

 

Grid Projects Energised

One project powering two institutions was energised in the week under review

Chivare Clinic & Business Centre in Shamva district ward 18 – 3.2km of 11kV line, 0.72km MV line and 50kVA substation capacity energized on 30/05/25 benefiting 4 shops serving a population of around 4195 in the ward. The Clinic is not yet operational.

 

Work Done last week

3 projects are in progress to electrify 3 institutions in various Districts

–  1.2km of HV line survey completed

–  0.97km of MV line survey completed

– Material for 3 projects delivered to site

 

Institutional Biogas Works in progress

– Pit excavation for Mazowe VET College Biogas 50m3   and St Alberts High School Biogas 50m3 in Mt Darwin are now complete, mobilisation of construction materials is in progress.

–  Shamva Hospital and Jiti Secondary School in Shamva pit excavations are in progress.

Domestic Biogas Works in Progress

Identification of interested villagers is in progress.

·  To date, 40 homesteads (8 homesteads in Rushinga, 8 homesteads in Mt Darwin, 8 homesteads in Bindura, 8 homesteads in Shamva and 8 Homesteads in Mazowe) were identified and have started mobilising local materials and excavation of pits in preparation for the dome construction.

· Muyembe homestead in Bindura District – domestic biogas pit excavation complete. Project is 50% complete.

  • Grid Projects Energised:

    Musipani Institutions (9) – Sivanga Pry Sch, Nyama BC, Musipani BC, Maketo Clinic, Musipani Community Hall, Musipani Arex, Musipani Vertinary Office & House, Utongani Sec Sch & Musipani Pry Sch) in Zvishavane District  – Scope: HV line 13km 11/18, 1 x 25kVA, 2 x 50kVA & 1 x 100kVA 11/0,4kV substations & 1.4km MV line. Energised on 27/05/25. The project benefited a total population of  Ward 6 and Ward 11 of Zvishavane District adding up to 15440.

    ·        Sivanga Pry –Ward 6,  8 households, 23 teachers, 615 students (306 boys & 309 boys), 6440 catchment area

    ·        Nyama BC – Ward 6, 13 households, 5000 catchment area

    ·        Musipani BC – Ward 11, 10 households & 1200 catchment area

    ·        Maketo Clinic – Ward 11, Households 4, Nurses 8, Catchment area 8000

    ·        Musipani AREX – Ward 11, Households 1, Catchment area 3000

    ·        Musipani Pry Sch – Ward 11, Households 13, teachers 22, students 548 (248 boys & 300 girls) Catchment area 1600

    ·        Utongani Sec Sch – Ward 11, Households 9, Teachers 20, Students 408, Catchment area 1400

    ·        Musipani Vertinary Office & house – Ward 11, Households 2, Officers 2, Catchment area 6000

    ·        Musipani Community hall – Ward 11, Household 1, Catchment area 9000

     

    Work Done last Week: 

    1 project was in progress to electrify 6 institutions.

    ·        6,025km HV line survey

    ·        1,5km HV bush clearing

    ·        2,926km HV line stringing

    ·        0,584km LV line survey and bush clearing

     

    Institutional Biogas:

    A visit to assess progress at Mvuma Pry Institutional Biogas was done.

    Hole excavation is in progress at Whawha Prison.

     

    Domestic Biogas

    ·        1 site was assessed during the week.

    ·        28 Quotations & BOQ’s were sent to customers.

     

    Community Solar Mini Grid Works in Progress:

    ·        Gandavaroyi Institutions – Project energised in April,

    ·        Works in progress on the septic tank and sprucing up of the guard room.

     

    Institutional Solar Micro Grid:

    ·        MV line construction preparations were finalised for Mhumha Pry School.

     

  • Stand No. 6020 Nyakamete Mutare
  • General Line:  +263-2020- 66536

Have you ever been ignored by REF staff members at any of our offices? Have you ever been wronged by REF staff members at any of our offices? Have you seen any of our vehicles being misused? Do you have any suggestions for REF efficiency?

Contact REF decision Makers on the numbers below

REF Board Chairman

REF Chief Executive

Executive Director Projects

Executive Director Planning & Technology

Executive Director Finance

Message Us on WhatsApp